Mormon Flat Dam Project

Job Description

Inside of chamber is to be blasted and inspected before starting per spec. After inspection is completed on welds and blasting, we will stripe welds where necessary in an Industrial coating. After inspection of weld striping, and interior chamber it’s to be primed in International 670 HS. After inspection of the prime coat is completed, the top coat of International 670 HS will be applied and inspected. All coatings to be applied at DFT of 6 mils.